P Free Exam Prep Hub Open Flashcards

Memorize fewer formulas by knowing what each one is trying to tell you.

PMP formula practice should support decision-making, not become the whole study plan. Use this sheet to review the formulas most candidates expect to see, then drill explanations in the free PMP practice workspace.

Core PMP formulas to review

Formula Meaning Plain-English use
CV = EV - AC Cost variance Positive means under budget; negative means over budget.
SV = EV - PV Schedule variance Positive means ahead of planned value; negative means behind plan.
CPI = EV / AC Cost performance index Above 1.0 means cost-efficient; below 1.0 means cost-inefficient.
SPI = EV / PV Schedule performance index Above 1.0 means progressing faster than planned; below 1.0 means slower.
EAC = BAC / CPI Estimate at completion Forecast total cost when current cost performance is expected to continue.
TCPI = (BAC - EV) / (BAC - AC) To-complete performance index Shows the efficiency needed on remaining work to finish on the original budget.
Channels = n(n - 1) / 2 Communication channels More stakeholders can sharply increase communication complexity.
PERT = (O + 4M + P) / 6 Three-point estimate Weights the most likely estimate more heavily than optimistic or pessimistic cases.
EMV = probability x impact Expected monetary value Compares risk choices using weighted financial exposure or opportunity.

How to drill PMP formulas

Translate signs first

Before solving, know whether positive, negative, above 1.0, or below 1.0 indicates a problem.

Connect to decisions

The exam often cares what the project manager should do next, not only the calculation.

Use short drills

Formula recall works best as repeated small practice sessions mixed with scenario questions.

This cheat sheet is an independent study aid. It does not reproduce official PMI exam questions or official PMI copyrighted prep content.

Review PMP flashcards