Translate signs first
Before solving, know whether positive, negative, above 1.0, or below 1.0 indicates a problem.
PMP formulas cheat sheet
PMP formula practice should support decision-making, not become the whole study plan. Use this sheet to review the formulas most candidates expect to see, then drill explanations in the free PMP practice workspace.
Formula table
| Formula | Meaning | Plain-English use |
|---|---|---|
| CV = EV - AC | Cost variance | Positive means under budget; negative means over budget. |
| SV = EV - PV | Schedule variance | Positive means ahead of planned value; negative means behind plan. |
| CPI = EV / AC | Cost performance index | Above 1.0 means cost-efficient; below 1.0 means cost-inefficient. |
| SPI = EV / PV | Schedule performance index | Above 1.0 means progressing faster than planned; below 1.0 means slower. |
| EAC = BAC / CPI | Estimate at completion | Forecast total cost when current cost performance is expected to continue. |
| TCPI = (BAC - EV) / (BAC - AC) | To-complete performance index | Shows the efficiency needed on remaining work to finish on the original budget. |
| Channels = n(n - 1) / 2 | Communication channels | More stakeholders can sharply increase communication complexity. |
| PERT = (O + 4M + P) / 6 | Three-point estimate | Weights the most likely estimate more heavily than optimistic or pessimistic cases. |
| EMV = probability x impact | Expected monetary value | Compares risk choices using weighted financial exposure or opportunity. |
Study tips
Before solving, know whether positive, negative, above 1.0, or below 1.0 indicates a problem.
The exam often cares what the project manager should do next, not only the calculation.
Formula recall works best as repeated small practice sessions mixed with scenario questions.
This cheat sheet is an independent study aid reviewed by Free Exam Prep Hub editorial review. It does not reproduce official PMI exam questions or official PMI copyrighted prep content. Use it with the PMP Hub, PMP practice test, PMP flashcards, PMP study plan, and timed simulator support.
PMP formulas FAQ
Start with earned value formulas such as CV, SV, CPI, SPI, EAC, and TCPI, then review communication channels, PERT, and expected monetary value.
Do a short PMP practice set first if you know the basics. Use the formula sheet when missed questions show that earned value, scheduling, risk, or communication formulas are slowing you down.
Use simulator or practice-test results to find formula weaknesses, review this sheet, then return to PMP practice questions or flashcards until the formula meaning is automatic.